New School Construction Progress

This is a page is where we’ll share our new school progress as provided by our Owner’s Rep and/or General Contractor.

5 - Interior - Canyon Area QR Code 4 - Interior - Performance Area 2 - QR Code 3 - Interior - Performance Area QR Code 2 - Exterior - Main Entry QR Code 1 - Exterior - Courtyard QR Code


  • Here is a short time-lapse video we have put together of the construction site within the first month of construction. (August 7, 2022 – August 31, 2022)
  • July 11, 2022 – Artaic Total Project Summary Report 220711 Huerfano TPS Report (JUL 2022)
    • Guaranteed Maximum Pricing finalized June 20, 2022
    • Community Engagement – setup at Heritage Park in Walsenburg on July 15th 6pm -8pm to share new design with community and answer any questions.
    • Construction Start – August 8, 2022
    • Ground Breaking Ceremony – August 12, 2022